Kenya's Standard Method of Measurement, explained

A bill of quantities is only useful in a tender if every contractor prices the same thing. The Standard Method of Measurement (SMM) is the rulebook that makes that true: it fixes how each kind of work is measured, in which unit, and how it is described. Kenyan practice follows the East African SMM, organised into trade bills.

Conventions differ slightly between firms and editions, so confirm house rules with the QS who will sign the BOQ. The summary below is the structure JengaQS uses by default; every bill can be renamed or extended.

BillTradeWhat it measuresTypical units
01Preliminaries & General ConditionsLump sums for site set-up, insurance, security, water and power for the works, and the NCA levy (0.5% of contract sum).Sum / Item
02SubstructureExcavation, disposal, hardcore, blinding, foundations, damp-proof membrane and anti-termite treatment.m³, m², m
03Reinforced Concrete SuperstructureConcrete by class (e.g. C25/20), formwork to contact surfaces, and reinforcement by bar type and diameter.m³, m², kg
04WallingMasonry by material and thickness; openings over 0.5 m² deducted; hoop-iron reinforcement.m², m
05RoofingRoof coverings measured on slope, timbers by section, fascia, gutters and downpipes.m², m, No.
06Carpentry & JoineryDoors, frames, ironmongery and fitted joinery, enumerated with full descriptions.No., m
07MetalworkSteel windows, grilles, balustrades and gates.m², m, No.
08FinishesScreeds, plaster, tiling, ceilings and painting by number of coats; narrow widths in linear metres.m², m
09Plumbing & MechanicalPipework by material and diameter, sanitary appliances, tanks and testing.m, No., Item
10ElectricalLighting and power points with wiring, boards, earthing and testing; utility connection as a provisional sum.No., Item
11External Works & DrainagePaving, kerbs, manholes, drain runs by depth, septic tanks and fencing.m², m, No.
12Provisional Sums & Prime CostAllowances for undefined work and nominated suppliers, with attendance and profit.Sum

Three rules that catch people out

  1. Excavation is measured net, to the plan size of the foundation, with no allowance for working space unless the bill says so. Working space, if paid, is its own item.
  2. Formwork is measured to the faces in contact with concrete; soffits and sides are separate items because they cost differently.
  3. Reinforcement is measured in kilograms by bar type and diameter (Y = high-yield, R = mild steel), not in bars or tonnes of a mixed bundle.