Kenya's Standard Method of Measurement, explained
A bill of quantities is only useful in a tender if every contractor prices the same thing. The Standard Method of Measurement (SMM) is the rulebook that makes that true: it fixes how each kind of work is measured, in which unit, and how it is described. Kenyan practice follows the East African SMM, organised into trade bills.
Conventions differ slightly between firms and editions, so confirm house rules with the QS who will sign the BOQ. The summary below is the structure JengaQS uses by default; every bill can be renamed or extended.
| Bill | Trade | What it measures | Typical units |
|---|---|---|---|
| 01 | Preliminaries & General Conditions | Lump sums for site set-up, insurance, security, water and power for the works, and the NCA levy (0.5% of contract sum). | Sum / Item |
| 02 | Substructure | Excavation, disposal, hardcore, blinding, foundations, damp-proof membrane and anti-termite treatment. | m³, m², m |
| 03 | Reinforced Concrete Superstructure | Concrete by class (e.g. C25/20), formwork to contact surfaces, and reinforcement by bar type and diameter. | m³, m², kg |
| 04 | Walling | Masonry by material and thickness; openings over 0.5 m² deducted; hoop-iron reinforcement. | m², m |
| 05 | Roofing | Roof coverings measured on slope, timbers by section, fascia, gutters and downpipes. | m², m, No. |
| 06 | Carpentry & Joinery | Doors, frames, ironmongery and fitted joinery, enumerated with full descriptions. | No., m |
| 07 | Metalwork | Steel windows, grilles, balustrades and gates. | m², m, No. |
| 08 | Finishes | Screeds, plaster, tiling, ceilings and painting by number of coats; narrow widths in linear metres. | m², m |
| 09 | Plumbing & Mechanical | Pipework by material and diameter, sanitary appliances, tanks and testing. | m, No., Item |
| 10 | Electrical | Lighting and power points with wiring, boards, earthing and testing; utility connection as a provisional sum. | No., Item |
| 11 | External Works & Drainage | Paving, kerbs, manholes, drain runs by depth, septic tanks and fencing. | m², m, No. |
| 12 | Provisional Sums & Prime Cost | Allowances for undefined work and nominated suppliers, with attendance and profit. | Sum |
Three rules that catch people out
- Excavation is measured net, to the plan size of the foundation, with no allowance for working space unless the bill says so. Working space, if paid, is its own item.
- Formwork is measured to the faces in contact with concrete; soffits and sides are separate items because they cost differently.
- Reinforcement is measured in kilograms by bar type and diameter (Y = high-yield, R = mild steel), not in bars or tonnes of a mixed bundle.